Monday, December 10, 2012

Before and After on 3 Creek





Erosion 3 Creek Continues

After two trees were removed, the area was graded.  This removed soil that has been moved around during flooding and provided a base for rocks to be installed to prevent erosion.


Next the cart path was removed because the creek had been undercutting it.


Then a heavy erosion fabric was installed in order to keep the rocks from settling into the sub-soil.


Then rocks were stacked on the liner starting at the water level and moving up.


After the rocks were stacked the crew filled any holes in the slope by hand with smaller rocks to strengthen the slope.


Once the rock work was done, forms were set and concrete was poured.


 The area around the new cart path was graded and grass was planted in areas where the soil was disturbed.





Wednesday, December 5, 2012

Erosion Work on 3 Begins

Scott Peck and Professional Golf Services arrived this week to begin erosion repair work on the creek between 2 and 3.  They are going to repair the section along 3 cart path between the two live oaks.  This is the area with the most erosion and the cart path is in immediate danger of being compromised. In order to keep disruption to golf play to a minimum, this project will be done in sections so PGS will be back in the spring to continue repairing other areas on along the creek.


The cart path will be removed in this section in order to regrade the area properly.  It will be replaced once all of the dirt work is finished.





The Ash tree on the 3 fairway side and the leaning water oak that is rotten on the bottom will be removed.


Once the cart path is removed and the slope is graded, a fabric erosion liner will be installed and rock will be placed on top of it to prevent future erosion issues.





Completion pictures coming soon...

Monday, November 26, 2012

Thanks to Marshall Pottery, we have new flower pots around the golf fire pit.

Before...


After...


New Azalea Bed on 17

The old mulch area behind 17 green has been transfromed into an azalea bed.


First, irrigation was added to the area.


Then soil ammendments were added, including compost, peat moss, and topsoil.


Then it was all tilled in.


Then azaleas were planted.  Formosa and red ruffles varieties were used.


Wednesday, September 19, 2012

Range Bridge Project has Started

The project to improve the aesthetics around the range bridge began last week.  Landvisions is installing an apron on the east side of the bridge to stop the erosion caused during heavy rains.  This will allow the area to be mowed and maintained during periods of low rainfall.




They are also installing a retaining wall on the cart barn/putting green side of the bridge.  This will improve the look of the area and deal with any erosion issues on that side.  It will also establish a defined area for planting a flower bed with azaleas, crepe myrtles, and was myrtles.




Friday, September 7, 2012

Planet Air

Last Monday we used a new aerification method on the greens.  This process is called Planet Air.  It is a very aggressive spiker that leaves very little surface disruption.  It helps improve water infiltration down into the soil profile and also helps exchange gases from the rootzone with oxygen in the atmosphere.  It can not replace a core aerification however because it does not remove any thatch, but it is a good process to do during tournament season when healing time is important.




Tuesday, June 26, 2012

Dryject-ing greens.

This past Monday Dryject of North Texas came out and injected 26 tons of sand and soil ammendment into the greens.  Dryject uses water at 3200psi to 'blow' holes in the greens, which then creates a vacuum that pulls dry material into the holes.






It is one of the least invasive procedures that can be done to a putting surface that puts a lot of material in to the root zone.  Once the process is complete, the maintenance staff drags the greens with a soft drag mat, rolls the greens, and then they are ready to be mowed and played on.



Monday, June 18, 2012

Greens Aerification

Greens are being aerified on Monday June 18th.  The aerification process removes organic matter, as well as, alleviates compaction.  It also makes room for sand to be placed into the aerification holes which acts as a 'mini-renovation' of the soil profile that slows the aging process of our greens.  The process starts by fertilizing with an organic soil ammendment and a polymer coated potassium fertilizer.  Both of these products improve the soil structure and allow for an environment conducive to better root growth.  After soil ammendments are applied, the greens are topdressed with sand.



Topdressing 14 green.


Aerifying behind topdressing with 1/2 inch coring tines spaced 1.5 inches apart.


Another view of the plugs from the aerifier.


Dragging the cores to separate the organic matter from the existing soil.


Organic matter on top of the green.


Organic matter removed from the green.


Blowing organic matter off of the green.

Once this process is complete, the greens are fertilized with 13-2-13 at .3# of nitrogen per 1000 square feet and watered in.  This nitrogen will help the holes to grow in and provide a soluble source of potassium until the polymer coated potassium fertilizer that was worked into the soil can start to release.  The greens are rolled the next morning and will be mowed the next afternoon when the sand on the surface is dry.  Mowing in the afternoon will help reduce the amount of mess the mower will create and keep the amount of wear and tear down on the blades due to mowing in sandy conditions.  

The holes on the greens usually fill in after about a week, but don't look fully healed until two weeks later.  This year we will be doing a Dryject the Monday after aerfication.  Dryject pushes holes in the greens with high pressure water and creates a vacuum that will pull dry sand and soil ammendments into these holes.  This process actually makes the greens firmer because you're adding material to the green without taking anything out.  Also, doing it after a traditional core aerification will help to 'squeeze' the old holes shut and since the soil is already loosened by aerification, the affect of the dryject is greater.

If you would like more information about the Dryject process go to www.dryject.com or look for future post about the process.